Gaetz, Boyles help Holt residents after FPL solar farm breach
“I believe FPL dropped the ball” by allowing the solar farm breach to occur, Gaetz said at the meeting, which took place at Holt Fire District Station 21, 490 U.S. Highway 90.

The Kayak site, which has significant slope, encompasses about 500 acres south of Interstate 10 and off Trawick Creek Road. The breach occurred on June 8 after 7 inches of rain fell in a three-hour period.
The largest of the ensuing sediment discharges occurred along the Kayak site’s east boundary, where the east berm and embankment of a stormwater conveyance swale eroded.

Among other areas of concern, up to 5 feet of sand interspersed with red clay from an uncontrolled release of stormwater was found in a wetland nearly spanning the Wilkinson Creek valley.
“This sediment discharge completely filled and covered the channel of Wilkinson Creek to the extent its original course was difficult to visually discern,” officials said in FPL’s wetland and stream restoration plan for the Kayak site.
Gaetz, R-Niceville, and District 3 state Rep. Nathan Boyles, R-Holt, hosted Monday’s meeting, which focused on what led to the breach, what FPL is doing to fix it, and what the company will do to prevent another breach from occurring.
“We’re going to make sure FPL doesn’t fail at making it right,” Gaetz said.
Boyles, whose property in Holt was impacted by the runaway sediment, said the overall issue “is just as important to me, both personally and as your state representative.”

Later during the meeting, he said, “There were zero other stormwater ponds that failed in northwest Florida the day we had this rain event.”
Boyles added that he thinks FPL gets the message that it doesn’t receive a pass by chalking up the massive June 8 rainfall to “an act of God.”
J.T. Young, vice president and general manager of FPL Northwest Florida, and Mike Sole, FPL’s vice president of environmental services, answered questions from many of the more than 80 residents who attended the meeting.

“We are certainly focusing on making this right by strengthening and restoring our stormwater system at the Kayak Solar Energy site,” Young said.
The June 8 breach wasn’t the first time that residents living near the Kayak site had to deal with runaway sediment from the site.
In early 2024, when the solar energy center was being built, heavy rains led to large amounts of sediment being pushed into adjacent creeks and wetlands. An FPL official apologized for that particular mess and said the company would clean up the affected areas and continue to implement its stormwater management practices.
At Monday’s meeting, Young and Sole said that after the June 8 breach occurred, FPL crews began working seven days a week to remove sediment from affected areas, repair the Kayak site’s stormwater system, restore Wilkinson Creek, and make other improvements.
“It is unacceptable for these types of events to occur,” Sole, who once served as the secretary of the Florida Department of Environmental Protection, said of the breach. “We acknowledge that.”
He said crews have restored the Kayak site berm that failed and have placed sod to help stabilize it. Work continues on the installation of 2,000 linear feet of 24-foot-long sheet pile along the berm that failed “to ensure and give you the comfort that you’re not going to have that kind of breach again.”
The sheet pile goes 20 feet underground, and only 4 feet above grade, resulting in “a very strong, armored berm,” Sole said.

He said crews have also begun creating more capacity in the site’s existing stormwater ponds so more water can be held back and have installed more outfall structures along the site’s northern pond to improve the controlled release of water after a major rainfall.
A copy of the Kayak Solar Energy Center Wetland and Stream Restoration Plan is available at fpl.com/kayakrestoration.

In addition to other completed and ongoing interim improvements, the Kayak site’s overall stormwater system will undergo a complete redesign, which will be reviewed by an independent engineering firm, Sole said. The firm is HDR Engineering, which is based in Omaha, Nebraska and has offices in Crestview and Pensacola.
“Once the third-party engineer finishes their review, they’ll give us the results,” Sole said. “We will make any final changes to that final stormwater design, and we will then submit it to the DEP for their review and approval. Hopefully this will happen in a very quick period of time.”

Sole thanked residents at the meeting for their patience.
“None of you asked for this,” he said of the solar farm breach. “None of you deserve having this disturbance in your life. Again, we thoroughly apologize but appreciate your patience as we move forward to try to make this right.”
Near the end of the meeting, Gaetz encouraged residents to contact him or Boyles if FPL fails to give the residents straight answers to their questions about the restoration of the Kayak site and adjacent areas.
“We will hold FPL accountable and get a straight answer,” Gaetz said.
District 3 Okaloosa County Commissioner Sherri Cox, who was unable to attend the meeting in Holt because of a personal matter, said at Tuesday’s commission meeting that residents also can contact her with any concerns they might have about the restoration work.

Cox said she has visited the Kayak site several times and has talked with several homeowners who have been affected by the breach.
“I’m pleased to say that, by my best estimates and the hundreds and hundreds of dump trucks and (pieces of) earth-moving equipment that are out there, they do appear to be making their best effort and being a good community partner in this,” Cox said of FPL. “It will take time and patience.”



























